Khimti-2 Hydroelectric Projectखिम्ती-२ जलविद्युत आयोजना
A 48.8 MW run-of-river project on the Khimti River in Dolakha, developed by the private sector under an EPCF model. As of 2024 physical progress was about 70%, with the dam, tunnel and powerhouse advancing toward completion.
Installed capacity
49 MW
Run-of-river
River / basin
Khimti
Koshi basin
Location
Dolakha
Bagmati
Expected online
2027
Under construction
Milestones & projected timeline
Key dates so far, with planned milestones marked. Future dates are targets from the developer or government and frequently shift.
- 2024
~70% physical progress
- 2027Planned
Expected commissioning
Location
Approximate dam-area location on OpenStreetMap — precise to the district and river reach, not the exact structure.
Sources & data note
Figures for Khimti-2 Hydroelectric Project are compiled from the sources below and cross-checked where possible. Status and projected dates reflect research as of mid-2026 and may change as the project progresses. The map location is an approximate dam-area estimate. Commentary is Amarnepal's own.