AmarnepalBudget Analysis
OperationalCommissioned 2024

Middle Tamor Hydropower Projectमध्य तमोर

A 73 MW run-of-river plant on the Tamor River in Taplejung, developed by Sanima Middle Tamor Hydropower Ltd (Sanima Group). Commercial operation began on 12 April 2024.

Installed capacity

73 MW

Run-of-river

River / basin

Tamor

Koshi basin

Location

Taplejung

Koshi

Commissioned

2024

Operational

How it was built

Milestones to commissioning

The route from construction to commercial operation.

  1. 12 Apr 2024

    Commercial operation began

On the map

Location

Approximate dam-area location on OpenStreetMap — precise to the district and river reach, not the exact structure.

Loading map…
Filter by stageTiles © OpenStreetMap contributors

Sources & data note

Figures for Middle Tamor Hydropower Project are compiled from the sources below and cross-checked where possible. Status and projected dates reflect research as of mid-2026 and may change as the project progresses. The map location is an approximate dam-area estimate. Commentary is Amarnepal's own.