AmarnepalBudget Analysis
OperationalCommissioned 2019

Kulekhani III Hydroelectric Projectकुलेखानी-३

A 14 MW NEA plant in Makwanpur that reuses the tailwater discharged by Kulekhani II, completing the Kulekhani cascade. With two 7 MW Francis units, it began trial generation in October 2019 after more than a decade in development.

Installed capacity

14 MW

Run-of-river

River / basin

Kulekhani (Rapti)

Bagmati basin

Location

Makwanpur

Bagmati

Commissioned

2019

Operational

How it was built

Milestones to commissioning

The route from construction to commercial operation.

  1. 2008

    Construction began

  2. 2 Oct 2019

    First 7 MW unit entered test operation

  3. 11 Oct 2019

    Second 7 MW unit entered test operation

On the map

Location

Approximate dam-area location on OpenStreetMap — precise to the district and river reach, not the exact structure.

Loading map…
Filter by stageTiles © OpenStreetMap contributors

Sources & data note

Figures for Kulekhani III Hydroelectric Project are compiled from the sources below and cross-checked where possible. Status and projected dates reflect research as of mid-2026 and may change as the project progresses. The map location is an approximate dam-area estimate. Commentary is Amarnepal's own.