AmarnepalBudget Analysis
OperationalCommissioned 2023

Ghar Khola Hydropower Projectघर खोला

A 14 MW run-of-river plant on the Ghar Khola in Myagdi, developed by Myagdi Hydropower Ltd, part of the cluster of projects turning Myagdi into a hydropower hub.

Installed capacity

14 MW

Run-of-river

River / basin

Ghar Khola

Gandaki basin

Location

Myagdi

Gandaki

Commissioned

2023

Operational

How it was built

Milestones to commissioning

The route from construction to commercial operation.

  1. 24 Aug 2023

    Commercial operation began (2080 Bhadra 08 BS)

On the map

Location

Approximate dam-area location on OpenStreetMap — precise to the district and river reach, not the exact structure.

Loading map…
Filter by stageTiles © OpenStreetMap contributors

Sources & data note

Figures for Ghar Khola Hydropower Project are compiled from the sources below and cross-checked where possible. Status and projected dates reflect research as of mid-2026 and may change as the project progresses. The map location is an approximate dam-area estimate. Commentary is Amarnepal's own.