A 44 MW run-of-river plant on the Madi Khola in Madi Rural Municipality, Kaski, with a net head of about 295 m. Promoted by Super Madi Hydropower Ltd (incorporated in 2009 and listed on NEPSE as SMHL), it began supplying test energy to the grid in 2025 after a long build.
Installed capacity
44 MW
Run-of-river
River / basin
Madi Khola
Gandaki basin
Location
Kaski
Gandaki
Commissioned
2025
Operational
Milestones to commissioning
The route from construction to commercial operation.
- 2009
Company incorporated to develop the project
- Mar 2025
Test production began
Supplied energy to NEA during a 15-day trial run before commercial operation
Location
Approximate dam-area location on OpenStreetMap — precise to the district and river reach, not the exact structure.
Sources & data note
Figures for Super Madi Hydroelectric Project are compiled from the sources below and cross-checked where possible. Status and projected dates reflect research as of mid-2026 and may change as the project progresses. The map location is an approximate dam-area estimate. Commentary is Amarnepal's own.