AmarnepalBudget Analysis
OperationalCommissioned 2019

Lower Hewa Khola Hydropower Projectतल्लो हेवा खोला

A 22.1 MW run-of-river plant in Panchthar drawing on the Hewa and Pheme kholas, developed by Mountain Hydro Nepal Ltd (listed on NEPSE). It began generating in 2019.

Installed capacity

22 MW

Run-of-river

River / basin

Hewa Khola

Koshi basin

Location

Panchthar

Koshi

Commissioned

2019

Operational

How it was built

Milestones to commissioning

The route from construction to commercial operation.

  1. 6 Aug 2019

    Commercial operation began

On the map

Location

Approximate dam-area location on OpenStreetMap — precise to the district and river reach, not the exact structure.

Loading map…
Filter by stageTiles © OpenStreetMap contributors

Sources & data note

Figures for Lower Hewa Khola Hydropower Project are compiled from the sources below and cross-checked where possible. Status and projected dates reflect research as of mid-2026 and may change as the project progresses. The map location is an approximate dam-area estimate. Commentary is Amarnepal's own.