AmarnepalBudget Analysis
OperationalCommissioned 1986

Kulekhani II Hydropower Stationकुलेखानी-२

A 32 MW cascade plant downstream of Kulekhani I in Makwanpur, using tailwater from the Kulekhani storage scheme. Owned by NEA and commissioned in 1986.

Installed capacity

32 MW

Reservoir

River / basin

Kulekhani

Bagmati basin

Location

Makwanpur

Bagmati

Commissioned

1986

Operational

How it was built

Milestones to commissioning

The route from construction to commercial operation.

  1. 1986

    Commissioned

On the map

Location

Approximate dam-area location on OpenStreetMap — precise to the district and river reach, not the exact structure.

Loading map…
Filter by stageTiles © OpenStreetMap contributors

Sources & data note

Figures for Kulekhani II Hydropower Station are compiled from the sources below and cross-checked where possible. Status and projected dates reflect research as of mid-2026 and may change as the project progresses. The map location is an approximate dam-area estimate. Commentary is Amarnepal's own.