A 57 MW run-of-river project in Dordi Rural Municipality, Lamjung, on the upper Dordi Khola, developed by People's Hydropower Company Ltd, extending the Dordi corridor further upstream.

Installed capacity

57 MW

Run-of-river

River / basin

Dordi Khola

Gandaki basin

Location

Lamjung

Gandaki

Expected online

2027

Under construction

Project timeline

Milestones & projected timeline

Key dates so far, with planned milestones marked. Future dates are targets from the developer or government and frequently shift.

  1. Under construction

    Construction ongoing in Dordi RM, Lamjung

  2. 2027

    Targeted commissioning

On the map

Location

Approximate dam-area location on OpenStreetMap — precise to the district and river reach, not the exact structure.

Loading map…
Filter by stageTiles © OpenStreetMap contributors

Sources & data note

Figures for Himchuli Dordi Hydropower Project are compiled from the sources below and cross-checked where possible. Status and projected dates reflect research as of mid-2026 and may change as the project progresses. The map location is an approximate dam-area estimate. Commentary is Amarnepal's own.