Dudhkoshi-2 (Jaleshwor) Hydroelectric Projectदूधकोशी-२ (जलेश्वर)
A 70 MW run-of-river project on the Dudh Koshi in Solukhumbu, developed by Dudh Koshi Hydropower Nepal Ltd. It achieved financial closure in 2025 with a roughly four-year construction target.
Installed capacity
70 MW
Run-of-river
River / basin
Dudh Koshi
Koshi basin
Location
Solukhumbu
Koshi
Expected online
TBD
Under construction
Milestones & projected timeline
Key dates so far, with planned milestones marked. Future dates are targets from the developer or government and frequently shift.
- Sep 2025
Financial closure secured (debt:equity 70:30)
- Kartik 2082 (late 2025)
Construction targeted to begin; ~4-year build
Location
Approximate dam-area location on OpenStreetMap — precise to the district and river reach, not the exact structure.
Sources & data note
Figures for Dudhkoshi-2 (Jaleshwor) Hydroelectric Project are compiled from the sources below and cross-checked where possible. Status and projected dates reflect research as of mid-2026 and may change as the project progresses. The map location is an approximate dam-area estimate. Commentary is Amarnepal's own.