AmarnepalNepal Data
Infrastructure & transport

MCC Nepal Compact Explained: Transmission Line & Road Project Tracker

The MCC Nepal Compact is a US$747 million grant program - US$550 million from the United States' Millennium Challenge Corporation and US$197 million from the Government of Nepal - that funds a 297-km, 400 kV electricity transmission line, three large substations and upgrades to the East-West Highway. Signed in 2017 and ratified in February 2022 after fierce political debate, it entered into force on 30 August 2023, survived the 2025 US foreign-aid freeze, and must be completed by August 2028.

Signed14 September 2017 (Bhadra 29, 2074 BS), Washington, DC
Total program valueAbout US$747 million (US$550m US grant + US$197m Government of Nepal)
Original US grantUS$500 million; raised by US$50 million in December 2024
Ratified by Parliament27 February 2022 (Falgun 15, 2078 BS), with a 12-point interpretive declaration
Entry into force30 August 2023 (Bhadra 13, 2080 BS)
Completion deadlineAugust 2028 (five years from entry into force)
Transmission line297 km of 400 kV lines, plus an 18-km cross-border section towards Gorakhpur, India
New substationsRatmate (Nuwakot), New Damauli (Tanahun), New Butwal (Nawalparasi West)
Implementing agencyMillennium Challenge Account Nepal (MCA-Nepal), established 18 April 2018
In depth

What is the MCC Nepal Compact?

The Millennium Challenge Corporation (MCC) is an independent United States foreign-assistance agency, created by the US Congress in 2004, that provides large, time-bound grants known as 'compacts' to selected developing countries that meet its policy performance criteria. MCC's board selected Nepal for compact development in December 2014, and on 14 September 2017 (Bhadra 29, 2074 BS) the two governments signed the MCC Nepal Compact in Washington, DC, making Nepal the first country in South Asia to sign an MCC compact. Nepal's then finance minister Gyanendra Bahadur Karki signed on behalf of the Government of Nepal.

The compact began as a US$500 million US grant - the largest single grant Nepal had received from the United States - paired with a US$130 million Nepali contribution. Nepal raised its share by US$67 million in May 2023 to US$197 million, which MCC calls the largest up-front partner-country contribution in its history, and in December 2024 the MCC board approved a further US$50 million to bridge a transmission-line cost gap, lifting the US grant to US$550 million and the total program to about US$747 million. The money is entirely grant assistance: it is not a loan and carries no repayment obligation.

The program is implemented by the Millennium Challenge Account Nepal (MCA-Nepal), a Government of Nepal agency established on 18 April 2018 under the Development Committee Act, 2013 BS (1956 AD), with a board chaired by the Secretary of the Ministry of Finance. Under MCC rules the compact runs on a strict five-year clock from its entry into force, and the Government of Nepal has designated the electricity component a 'national pride project'.

MCC transmission line Nepal: the 297-km, 400 kV electricity backbone

The Electricity Transmission Project is the heart of the compact, with roughly US$399 million allocated according to MCC. Its goal is to strengthen Nepal's high-voltage backbone so that electricity generated by new hydropower plants can actually reach consumers, reduce load-shedding risk and technical losses, and open a high-capacity route for power trade with India. MCC estimates about 22.7 million people will benefit from the electricity investments over their lifetime.

The project builds a 297-kilometre network of 400 kV transmission lines - among the highest-capacity lines ever built in Nepal - together with three new 400 kV substations at Ratmate (Nuwakot district), New Damauli (Tanahun district) and New Butwal (Nawalparasi West district). Earlier project documents cited a total of around 300-315 km; the final design settled at 297 km for the main network, plus a separate 18-km cross-border section. Once complete, Ratmate and New Damauli are expected to rank among Nepal's largest high-voltage substations.

The cross-border element connects the New Butwal substation towards Gorakhpur in India's Uttar Pradesh. MCA-Nepal fast-tracked the 18-km Nepali section as a separate contract (Transrail Lighting Limited, about US$12.36 million) so it could be ready in step with the Indian portion, which is being developed by a joint venture involving the Nepal Electricity Authority and India's Power Grid Corporation. Together with the existing Dhalkebar-Muzaffarpur line, the Butwal-Gorakhpur link is central to Nepal's plan to export surplus wet-season hydropower.

  • Lapsiphedi-Ratmate-New Hetauda section: about 117 km, linking the Kathmandu Valley's edge to the central grid (contractor: Ashish-Bozlar JV)
  • Ratmate-New Damauli section: roughly 90 km westward along the hill corridor (contractor: Angelique-Skipper JV)
  • New Damauli-New Butwal section: roughly 90 km down to the western Tarai (contractor: Waiba-Salasar JV)
  • Three new 400 kV substations: Ratmate (Nuwakot), New Damauli (Tanahun) and New Butwal (Nawalparasi West)
  • 18-km cross-border section from New Butwal towards Gorakhpur, India, procured separately for speed

The Road Maintenance Project on the East-West Highway

The compact's second component, the Road Maintenance Project, has an allocation of about US$52.3 million. Its purpose is to lower Nepal's very high road-transport costs by demonstrating modern, preventive maintenance on the strategic road network - covering up to about 90 kilometres of highway according to MCC - rather than the rebuild-after-failure cycle that has dominated Nepali road management. The project also funds technical assistance and an incentive mechanism to encourage the government to budget for periodic maintenance.

In December 2025 MCA-Nepal signed two contracts worth US$23.66 million: a US$20 million construction contract with the Sharma-Kumar Joint Venture to upgrade the 40-km Dhan Khola-Lamahi stretch of the East-West (Mahendra) Highway in Dang district, and a US$3.66 million supervision contract with Intercontinental Consultants and Technocrats Pvt Ltd that also covers periodic maintenance of the busy Narayanghat-Muglin road. Physical works on the Dhan Khola-Lamahi section began in late April 2026 (Baisakh 2083 BS).

The Dang works introduce two technologies new to Nepal at this scale: full-depth reclamation (FDR), which recycles the existing pavement in place instead of trucking in fresh aggregate, and Superpave asphalt design, used widely in the United States for longer-lasting road surfaces. The upgraded highway section will be about 12 metres wide, with a 7-metre carriageway and 2.5-metre shoulders on both sides. MCC estimates roughly 925,000 beneficiaries from the road investments.

From signing to ratification: why the MCC compact was so controversial

Although signed in 2017, the compact sat unratified for nearly four and a half years. It was tabled in the House of Representatives on 15 July 2019, but stalled as Nepal's major parties split over it. Opposition intensified after visiting US officials in 2019 publicly framed MCC assistance as part of the US Indo-Pacific Strategy, feeding claims that the compact was a security arrangement rather than a development grant. Critics argued that provisions on intellectual property, audits and the compact's precedence over domestic law compromised sovereignty, while social-media misinformation went further, alleging it would bring American troops to Nepal.

In September 2021 Nepal's Ministry of Finance sent MCC a list of written questions, and MCC replied that the compact is not part of the Indo-Pacific Strategy, involves no military component, and that Nepal remains free to exit the agreement. With MCC signalling that its board would review the compact's future at the end of February 2022, the ruling coalition moved it through parliament under intense pressure, even as two coalition partners simultaneously supported street protests against it.

On 27 February 2022 (Falgun 15, 2078 BS) the House of Representatives ratified the compact by majority alongside a 12-point 'interpretive declaration'. The declaration states, among other points, that Nepal will not be part of any US strategic, military or security alliance - including the Indo-Pacific Strategy - and that the Constitution of Nepal prevails over the compact. Demonstrators clashed with police outside parliament that day, with tear gas, water cannons and rubber bullets used to disperse stone-throwing crowds. MCC formally acknowledged the declaration, and around the compact's entry into force in August 2023 it reiterated in writing that Nepal's constitution prevails over the agreement.

  • December 2014: MCC board selects Nepal for compact development
  • 14 September 2017 (Bhadra 29, 2074 BS): compact signed in Washington, DC
  • 18 April 2018: MCA-Nepal established as the implementing agency
  • 15 July 2019: compact tabled in Nepal's House of Representatives
  • 27 February 2022 (Falgun 15, 2078 BS): parliament ratifies with a 12-point interpretive declaration
  • 30 August 2023 (Bhadra 13, 2080 BS): compact enters into force, starting the five-year clock
  • May 2023 / December 2024: Nepal adds US$67 million; MCC board approves US$50 million more, total about US$747 million
  • 2025: US aid freeze pauses the program in February; continuation confirmed in July
  • 10 June 2026: main groundbreaking for the 297-km line and Ratmate and New Damauli substations
  • August 2028: compact completion deadline

The 2025 US aid freeze: pause, review and resumption

On 20 January 2025 the new Trump administration issued an executive order freezing most US foreign assistance for review. On 18 February 2025 MCC notified Nepal that payments under the compact had been halted, and MCA-Nepal paused most activities. Because the compact must finish by August 2028 regardless of interruptions, even a short freeze raised fears that major works could run out of time, and Nepal's Ministry of Finance began examining fallback financing options.

The picture darkened in the spring of 2025, when reports emerged that the Department of Government Efficiency (DOGE) intended to drastically shrink MCC itself and wind down many of its compacts worldwide. In late March 2025, however, the US government authorised select MCA-Nepal activities to resume, keeping essential contracts alive while the broader review continued.

The uncertainty ended in July 2025. In a letter received by the Ministry of Finance on 23 July 2025, MCC confirmed that the US review of foreign assistance had concluded and recommended continuing the Nepal Compact, a decision the US Embassy in Kathmandu publicly affirmed within days. A senior MCC delegation visited Kathmandu in August 2025 as implementation restarted, and the final transmission-line construction contract was awarded in September 2025.

Construction tracker: where every MCC Nepal project stands

As of mid-2026 (Asar 2083 BS), every major component of the compact is under contract and in construction. The first construction contract was signed back in May 2024, when Linxon India Pvt Ltd was engaged to build the 400 kV New Butwal substation in Nawalparasi West on a roughly 39-month schedule. The fast-tracked 18-km cross-border line section from New Butwal towards the Indian border followed under Transrail Lighting Limited.

Procurement of the main 297-km line proved harder: MCA-Nepal relaunched the transmission-line tender in November 2024, and the freeze of early 2025 added delay. Contracts for the line packages and the two remaining substations were completed through 2025, and on 10 June 2026 MCA-Nepal formally broke ground at Ratmate in Nuwakot on the Ratmate and New Damauli substations and the 297-km line - the compact's largest single milestone so far.

The hard deadline shapes everything: MCC compacts end five years after entry into force, so funding stops in August 2028 whether or not works are finished, and any remaining tasks would fall to the Government of Nepal. Tower foundations across roughly 300 km of hill terrain, forest clearances and land-access issues along the right-of-way are the main risks to watch between now and 2028.

  • New Butwal substation (Nawalparasi West): under construction by Linxon India Pvt Ltd; contract signed May 2024, about 39 months' duration
  • 18-km cross-border section (New Butwal towards Gorakhpur): Transrail Lighting Limited, contract worth about US$12.36 million
  • Ratmate and New Damauli substations: Techno Electric and Engineering Company Ltd (India); groundbreaking 10 June 2026
  • 297-km, 400 kV line: Ashish-Bozlar JV (Lapsiphedi-Ratmate-New Hetauda, 117 km), Angelique-Skipper JV (Ratmate-New Damauli) and Waiba-Salasar JV (New Damauli-New Butwal); final contract awarded September 2025
  • Road Maintenance Project: 40-km Dhan Khola-Lamahi upgrade in Dang under way since April 2026 (Sharma-Kumar JV), plus Narayanghat-Muglin periodic maintenance
  • Deadline: all compact-funded works must finish by August 2028

Why the MCC compact matters for Nepal's energy and economy

Nepal's installed hydropower capacity has grown rapidly, but its transmission grid has not kept pace: generation projects in the Trishuli, Marsyangdi and other river corridors routinely face bottlenecks getting power to load centres, and surplus wet-season electricity is wasted when it cannot be exported. The compact's 400 kV backbone - running from Lapsiphedi on the Kathmandu Valley's rim through Ratmate, New Hetauda, New Damauli and New Butwal - is designed to relieve exactly this constraint, roughly paralleling one-third of the country's length.

The New Butwal-Gorakhpur interconnection gives Nepal a second high-capacity gateway to the Indian market alongside Dhalkebar-Muzaffarpur, supporting the government's ambition to scale up electricity exports to India and, eventually, Bangladesh. MCC's own economic analysis projects an estimated 12 percent economic rate of return on the electricity project and about 29 percent on the road works. For ordinary consumers, the promised gains are more reliable supply, lower system losses and a grid able to absorb the next generation of hydropower plants.

The compact is also a test case with wider significance: it is MCC's flagship program in South Asia, and it survived both Nepal's most divisive foreign-aid debate in decades and a sweeping US aid retrenchment. Whether the towers are strung and the substations energised by August 2028 will be one of the clearest measures of Nepal's ability to deliver large infrastructure on time.

Questions

MCC Nepal Compact Explained: Transmission Line & Road Project Tracker — FAQ

What is MCC Nepal?+

MCC Nepal refers to the Millennium Challenge Corporation's Nepal Compact, a US$747 million infrastructure grant program funded by a US$550 million US grant and a US$197 million Government of Nepal contribution. It finances a 297-km, 400 kV electricity transmission line with three large substations and upgrades to the East-West Highway. The program is implemented by MCA-Nepal, a Government of Nepal agency, and must be completed by August 2028.

Is the MCC 500 million for Nepal a grant or a loan?+

It is a grant, not a loan - Nepal does not repay any of it. The original US contribution was US$500 million, increased to US$550 million after the MCC board approved additional funding in December 2024. Nepal separately contributes US$197 million of its own budget to the same projects.

Where does the MCC transmission line in Nepal go?+

The 297-km, 400 kV network runs in three sections: Lapsiphedi-Ratmate-New Hetauda (about 117 km), Ratmate-New Damauli, and New Damauli-New Butwal, with new 400 kV substations at Ratmate (Nuwakot), New Damauli (Tanahun) and New Butwal (Nawalparasi West). A separate 18-km section extends from New Butwal towards the Indian border, forming the Nepali side of the planned Butwal-Gorakhpur cross-border interconnection.

Why was the MCC compact controversial in Nepal?+

Critics feared the compact tied Nepal to the US Indo-Pacific Strategy, undermined sovereignty because the agreement would prevail over domestic law, and - in widely circulated misinformation - could even bring US troops to Nepal. MCC responded in writing in 2021 that the compact has no military component, and parliament ratified it on 27 February 2022 together with a 12-point interpretive declaration affirming that Nepal's constitution prevails and Nepal joins no security alliance. Protests outside parliament that day were dispersed with tear gas and water cannons.

Is the MCC Nepal Compact still active after the 2025 US aid freeze?+

Yes. The compact was paused in February 2025 under the Trump administration's foreign-aid freeze, but after a review the US confirmed its continuation in a letter received by Nepal's Ministry of Finance on 23 July 2025. Work has since accelerated: the final transmission-line contract was awarded in September 2025, and groundbreaking on the main line and two substations took place on 10 June 2026.

When will the MCC Nepal projects be completed?+

All compact-funded works must be finished by August 2028, five years after the compact entered into force on 30 August 2023, because MCC funding ends on that date regardless of progress. The New Butwal substation has been under construction since 2024, the main 297-km line and the other two substations broke ground in June 2026, and the 40-km Dhan Khola-Lamahi road upgrade began in April 2026.

Related topics

← All topics