Dedicated Feeder & Trunk Line Premium Tariff: Nepal's NEA Dispute Explained
During Nepal's load-shedding years, the Nepal Electricity Authority (NEA) supplied favoured industries uninterrupted power through 'dedicated feeders' and 'trunk lines' and charged a premium tariff for it. Factories dispute over Rs 22 billion in back-dated bills, arguing they never got the promised round-the-clock supply and that the tariff lacked proper approval. A former Supreme Court judge's panel proposed waiving charges for two periods, but the row keeps returning to court, Parliament and the streets, with NEA repeatedly cutting industrial power over unpaid dues.
| What it is | Premium tariff NEA charged industries for uninterrupted power via dedicated feeders and trunk lines during load-shedding |
| Scheme approved / launched | NEA board 710th meeting, 27 June 2015; effect from ~August 2015 (mid-2072 BS) |
| Initial premium rate | About 65% over normal tariff (later reduced to ~15% above standard) |
| Daily supply offered | Up to ~24 hours (dedicated feeder); ~20 hours (trunk line) |
| Disputed dues (claimed) | Around Rs 22 billion across ~59-61 industrial consumers (up from Rs 10.14 billion claimed from 58 factories in 2018) |
| Settlement panel | Three-member panel led by ex-Supreme Court Justice Girish Chandra Lal, formed Jan 2024; report submitted May 2024 |
| Largest single claim | Jagdamba Steel, about Rs 4.14 billion (per NEA) |
| Recent power cuts | 6 industries cut in 2025, then ~18 more on ~24 Oct 2025 over dues exceeding Rs 8 billion |
| Governing law | Nepal Electricity Authority Act, 1984; Electricity Revenue Collection Regulations, 2078 BS |
What dedicated feeders and trunk lines actually are
A 'dedicated feeder' is a separate electricity line run directly from a substation to a single large consumer, usually a factory. Because the feeder is not shared with ordinary households, the Nepal Electricity Authority (NEA) could keep it energised even while surrounding areas were switched off during load-shedding. In practice this meant a dedicated-feeder industry could receive up to 24 hours of supply a day when everyone else had power for only a few hours.
A 'trunk line' is a related but distinct arrangement. Here the industry is connected closer to the transmission network, typically by installing a transformer inside the factory premises and drawing power routed through two substations. Trunk-line consumers were generally offered around 20 hours of daily supply during the crisis, slightly less than the near-continuous dedicated-feeder service.
Both schemes were a response to Nepal's severe electricity shortage, when scheduled outages ran to 12-18 hours a day in the worst winters. For energy-hungry sectors such as cement, steel, spinning and plastics, an interrupted grid meant idle machinery and spoiled batches, so paying extra for reliable power was commercially attractive. NEA first advertised the option of buying electricity through dedicated feeders around 20 October 2013, and it became widely used from 2015.
The core bargain was simple on paper: the industry got priority, near-uninterrupted electricity, and in return it paid a premium on top of the normal industrial tariff. The dispute that followed is essentially an argument about whether that bargain was honoured, whether the extra charge was ever legally fixed, and how much is genuinely owed.
- Dedicated feeder: separate line direct from a substation; up to ~24 hours/day supply.
- Trunk line: connection nearer the transmission grid via an in-factory transformer; ~20 hours/day supply.
- Both kept large industries running while ordinary areas faced daily load-shedding.
- Mainly used by cement, steel, spinning/textile and plastics factories in the Lumbini industrial corridor and elsewhere.
The premium tariff: how the extra charge was set
The premium originated with NEA's board of directors, which at its 710th meeting on 27 June 2015 approved additional charges for industries taking uninterrupted supply through dedicated feeders and trunk lines. The scheme took effect from around August 2015 (mid-2072 BS), in the depths of the load-shedding crisis. Initially NEA levied a premium of about 65 percent over the normal tariff, later reducing it to roughly 15 percent above the standard rate.
Because Nepal's electricity tariffs must be approved by an independent regulator, the timing of formal approval became central to the dispute. Reporting indicates the premium was only formalised by the Electricity Tariff Fixation Commission on 13 January 2016 (2072-09-29 BS), and NEA moved to implement it more concretely from 16 July 2016. Charges levied before formal approval are among the items industrialists and later investigators questioned.
The premium was meant to apply where a consumer genuinely drew power around the clock. To measure this, NEA in a September 2015 notice told factories to install Time-of-Day (TOD) meters, which record how many hours per day electricity is actually consumed. The idea was that if a TOD meter showed consistent consumption exceeding roughly 20 hours a day during blackout periods, the premium was justified.
In reality, the metering evidence became a weak point for NEA. Investigators later found that in many cases TOD meter data was never properly downloaded or presented, so NEA could not always prove that a given factory had actually taken the continuous supply it was being billed a premium for. That evidentiary gap is one reason billions of rupees in claims remain contested rather than settled.
Why billions in dues are disputed
The financial scale of the row grew steadily. In 2018 NEA wrote to 58 factories demanding about Rs 10.14 billion in outstanding premium charges. By 2023-2024 the claimed total across roughly 59-61 consumers had swelled beyond Rs 20 billion, with a review panel documenting a dispute of around Rs 22 billion in arrears. Individual claims are large: NEA alleged that Jagdamba Steel alone owed about Rs 4.14 billion.
Industrialists reject much of this. Their central argument is that they should pay a premium only for power they actually received continuously, yet NEA frequently could not produce meter data proving 24-hour supply. Several factories say the promised uninterrupted service was itself unreliable, so charging a full premium was unfair. Others contend they never used dedicated or trunk-line services at all and were billed in error.
The billing method compounded the mistrust. In 2019 NEA issued back-dated, consolidated bills covering roughly three years at once, sometimes after it had already suspended dedicated-feeder supply to the private sector (a suspension reported around 23 February 2016). Industrialists complained the bills were faulty, inconsistent and impossible to reconcile, and at one point NEA reportedly submitted a bundle running to about 100,000 pages to Parliament's Public Accounts Committee (PAC).
In short, the Rs 22-billion figure is not a settled debt but a contested claim. It mixes charges from periods before the tariff was formally approved, charges for a service whose delivery cannot always be evidenced, and interest and penalties accrued over years of stalemate, all of which the two sides value very differently.
The Lal Commission and the settlement panel
To break the deadlock, the government in January 2024 formed a three-member investigation panel chaired by former Supreme Court Justice Girish Chandra Lal, with joint secretaries from the energy and industry ministries as members. Its task was to examine the disputed dues, spread across factories concentrated in the Lumbini industrial corridor, and recommend a fair settlement to the government.
The Lal panel submitted its report in early May 2024. It concluded that NEA's billing had been problematic across distinct periods. For roughly mid-July 2015 to mid-January 2016, NEA had effectively set tariffs before proper approval, making some billing legally questionable. For the middle period (about February 2016 to May 2018) it found inconsistent and sometimes higher tariffs, including billing after services were suspended, and recommended recalculation. For the period after June 2018 it found no valid basis for the premium at all, because by then the government had declared load-shedding over and the special uninterrupted service was no longer meaningful.
On that basis the panel recommended waiving the premium for two windows: the first roughly six months of the scheme (mid-July 2015 to mid-January 2016) and the period after mid-2018, leaving a narrower core window (about mid-January 2016 to mid-May 2018) for which industries would genuinely owe premium charges. The report also flagged that of the industries involved, only a minority had completed the legal process, while many had gone to district courts under the Nepal Electricity Authority Act, 1984.
Even after the report, settlement proved politically fraught. NEA publicly worried that leniency toward industrialists would erode its revenue, while the government leaned toward a phased, negotiated recovery. NEA offered instalment plans stretching over 60 months, and some industries began paying instalments against the core-period charges, but a comprehensive, final settlement accepted by all sides has remained elusive.
Recent power cuts and the political fallout
Frustrated by non-payment, NEA has repeatedly used its strongest tool: disconnection. In late 2024 the Cabinet directed recovery of the outstanding dedicated-feeder and trunk-line dues, and NEA under managing director Kulman Ghising pressed hard to collect. This collection drive became entangled with national politics.
In March 2025 the government sacked Kulman Ghising, the widely credited 'light man' who had ended daily load-shedding, months before his term was due to end, and reinstated Hitendra Dev Shakya as NEA chief. The removal, which drew street protests, was officially blamed on missed performance reports and an unauthorised tariff understanding with India, but many observers linked it to the pressure Ghising's aggressive dues-recovery had put on powerful industrialists.
The disconnections continued regardless of who led NEA. In 2025 the authority cut power to a first batch of six large industries, including Jagadamba Steels, Reliance Spinning Mills, Shivam Cement, Triveni Spinning Mills, Ghorahi Cement and Arghakhanchi Cement, over unpaid dues. Later, around 24 October 2025, NEA disconnected a further 18 industries, among them Panchakanya Steel, Cosmos Cement, Bishal Cement, Butwal Cement and several others, citing unpaid dedicated and trunk-line dues exceeding Rs 8 billion, acting under the Electricity Revenue Collection Regulations, 2078 BS after a 21-day notice.
Industry bodies warn that mass disconnections threaten output and jobs, with some reports citing around 25 major industries affected and roughly 15,000 jobs at risk. Meanwhile the matter continues to move through the courts, the Public Accounts Committee and even the anti-corruption commission, keeping a dispute that began during the load-shedding era very much alive years after the lights came back on.
Why the dispute still matters
The dedicated-feeder row is more than an accounting quarrel. It tests whether a state utility can charge premium rates for a special service without airtight metering evidence and timely regulatory approval, and whether large consumers can be compelled to pay years-old, back-dated bills they never accepted in real time. The answers will shape how NEA prices reliability for industry in future.
It also sits at the intersection of energy policy, industrial competitiveness and governance. Cement, steel and textile plants are among Nepal's biggest domestic manufacturers; abrupt power cuts ripple through construction, exports and employment. At the same time, unrecovered dues weaken NEA's finances and raise fairness questions for consumers who paid their bills in full.
Finally, the saga has become a case study in how technical utility disputes get politicised. The removal of a popular NEA chief in the middle of a collection drive, the shuttling of the case between panels, courts and parliamentary committees, and the recurring disconnection notices all illustrate why the topic keeps resurfacing in Nepali public life, and why a neutral explanation of the facts is genuinely useful.
Dedicated Feeder & Trunk Line Premium Tariff: Nepal's NEA Dispute Explained — FAQ
What is a dedicated feeder and how does it differ from a trunk line in Nepal?+
A dedicated feeder is a separate electricity line run straight from a substation to one large consumer, so it can stay energised during load-shedding and give up to about 24 hours of daily supply. A trunk line connects an industry nearer the transmission grid, usually via a transformer inside the factory, and provided around 20 hours a day. Both let big industries keep running while ordinary areas faced daily outages.
What was the NEA premium tariff and why is it disputed?+
The Nepal Electricity Authority (NEA) charged industries extra, initially about 65 percent above the normal tariff (later cut to around 15 percent), for round-the-clock supply through dedicated feeders and trunk lines from 2015. It is disputed because the charge was arguably applied before formal regulatory approval, NEA often could not prove via meter data that a factory actually received continuous supply, and bills were issued back-dated and inconsistently.
How much money is at stake in the trunk line tariff dispute?+
NEA has claimed roughly Rs 22 billion in disputed arrears from around 59-61 industrial consumers, up from about Rs 10.14 billion demanded from 58 factories in 2018. Individual claims are large, such as an alleged Rs 4.14 billion against Jagdamba Steel. Because much of this is contested rather than admitted, the real recoverable figure is unsettled.
What did the Lal Commission recommend about the dedicated feeder dues?+
The panel led by former Supreme Court Justice Girish Chandra Lal (formed January 2024, reporting May 2024) recommended waiving the premium for two windows: roughly the first six months of the scheme (mid-2015 to early 2016) and the period after mid-2018 when load-shedding officially ended. Charges would mainly apply to the core window of about early 2016 to mid-2018, and it flagged NEA's failure to use TOD meter data.
Why did NEA cut power to industries recently?+
After years of unpaid premium bills and a Cabinet directive to recover the dues, NEA disconnected defaulting factories. In 2025 it cut power to six large industries and then to around 18 more on about 24 October 2025 over dues exceeding Rs 8 billion, acting under the Electricity Revenue Collection Regulations, 2078 BS after a 21-day notice. Industry groups warn the cuts endanger output and thousands of jobs.
How is the dedicated feeder dispute linked to Kulman Ghising's removal?+
Kulman Ghising, the NEA chief credited with ending load-shedding, led an aggressive drive to collect the disputed dedicated-feeder and trunk-line dues. In March 2025 the government sacked him months before his term ended, officially over performance reports and an unauthorised tariff understanding. Many observers connected the timing to the pressure his recovery campaign placed on powerful industrialists, though the government denied that link.
Related topics
Sources & data note
This article is compiled from the cited sources and contains durable facts only (no daily-changing data). Verify time-sensitive details with the relevant authority.
- NEA v Industries: Dedicated feeders and trunk lines controversy explainedOnlineKhabar ↗
- Dedicated and trunk line: Lal Commission report reveals Rs 22bn disputeThe Annapurna Express ↗
- Panel formed to settle dispute over power bills due to be paid by factoriesThe Kathmandu Post ↗
- NEA disconnects power supply to 18 industries over dedicated and trunkline dues exceeding Rs 8 billionFiscal Nepal ↗
- Explained: How NEA, Kulman Ghising, and unresolved tariff disputes are threatening Nepal's major industriesNepalnews ↗
- Everything you need to know about the government's dispute with Kulman Ghising and his removalNepalnews ↗
- Industries begin paying instalments in dedicated feeder and trunk line tariff disputeNew Business Age ↗
- Dedicated trunk line dispute: NEA to issue final warning, to disconnect power supply for non-paymentmyRepublica ↗